IDENTIFICATION OF CAUSES OF TIME AND COST OVERRUN, IT’S IMPACT AND CONTROL IN METRO PROJECTS IN INDIA

May 2022
Vol-8, Issue-3
Paper ID: 16868
ISSN: 2395-4396
Downloads: 0

Abstract & Details

Research Area
Civil Engineering
Keywords
Delay metro cost time budget management planning quality and schedule are all terms that can be used to describe a situation.
Abstract
Metro rail systems are required in cities not only to offer an efficient public transportation system, but also to reduce traffic and improve environmental conditions. Many cities already have metro rail plans in the works, but implementation is hampered by a number of issues. The goal of this study paper is to examine the primary causes of schedule and expense delays, as well as to collect data from a diverse group of construction experts working on Metro Projects using a questionnaire survey. The main conclusions drawn from the data should benefit the construction industry in better assessing not only the major causes of delays as well as the causes of delays in overall construction projects, but also how to reduce them through appropriate planning and the use of splitting working methods. Almost every metro project in India is running behind schedule. In megaprojects, delays are often regarded as the most common, challenging, and dangerous issue. The bulk of construction projects in underdeveloped countries have time overruns. All projects, regardless of their size or complexity, are plagued by deadlines and unpredictability. Every construction project encounters delays, which vary widely from one project to the next. Prior studies on time and cost overrun factors are thoroughly evaluated in this study. Aside from fulfilling the growing demand, sound decision-making throughout the construction phase can help to avoid delays. More research is needed, however. This might involve, among other things, research into decision-making procedures, the content of construction site management training programmes, the value of apprenticeship programmes in building a more skilled workforce, and the potential for expanded use of pre-cast materials. This study looked into the reasons for construction project delays in India.

Author Information

# Name Institute / Affiliation
1 Sonar Ketan Prabhakar JSPM's Rajarshi Shahu College of Engineering, Tathawade, Pune - 411033
2 Roshan Pramod More JSPM's Rajarshi Shahu College of Engineering, Tathawade, Pune - 411033
3 Rutuja Balasaheb Shinde JSPM's Rajarshi Shahu College of Engineering, Tathawade, Pune - 411033
4 Prof. Raj Bhosale JSPM's Rajarshi Shahu College of Engineering, Tathawade, Pune - 411033

How to Cite

Use the following formats to cite this article in your research.

APA Style
Prabhakar, Sonar Ketan, More, Roshan Pramod, Shinde, Rutuja Balasaheb, & Bhosale, Prof. Raj (2022). IDENTIFICATION OF CAUSES OF TIME AND COST OVERRUN, IT’S IMPACT AND CONTROL IN METRO PROJECTS IN INDIA. International Journal of Advance Research and Innovative Ideas In Education, 8(3), 1703-1713.
MLA Style
Prabhakar, Sonar Ketan, et al. "IDENTIFICATION OF CAUSES OF TIME AND COST OVERRUN, IT’S IMPACT AND CONTROL IN METRO PROJECTS IN INDIA." International Journal of Advance Research and Innovative Ideas In Education, vol. 8, no. 3, 2022, pp. 1703-1713.
IEEE Style
Sonar Ketan Prabhakar, Roshan Pramod More, Rutuja Balasaheb Shinde, and Prof. Raj Bhosale, "IDENTIFICATION OF CAUSES OF TIME AND COST OVERRUN, IT’S IMPACT AND CONTROL IN METRO PROJECTS IN INDIA," International Journal of Advance Research and Innovative Ideas In Education, vol. 8, no. 3, pp. 1703-1713, 2022.
Vancouver Style
Prabhakar Sonar Ketan, More Roshan Pramod, Shinde Rutuja Balasaheb, Bhosale Prof. Raj. IDENTIFICATION OF CAUSES OF TIME AND COST OVERRUN, IT’S IMPACT AND CONTROL IN METRO PROJECTS IN INDIA. International Journal of Advance Research and Innovative Ideas In Education. 2022;8(3):1703-1713.
Harvard Style
Prabhakar, Sonar Ketan, More, Roshan Pramod, Shinde, Rutuja Balasaheb, & Bhosale, Prof. Raj (2022) 'IDENTIFICATION OF CAUSES OF TIME AND COST OVERRUN, IT’S IMPACT AND CONTROL IN METRO PROJECTS IN INDIA', International Journal of Advance Research and Innovative Ideas In Education, 8(3), pp. 1703-1713.
Chicago Style
Prabhakar, Sonar Ketan, et al. "IDENTIFICATION OF CAUSES OF TIME AND COST OVERRUN, IT’S IMPACT AND CONTROL IN METRO PROJECTS IN INDIA." International Journal of Advance Research and Innovative Ideas In Education 8, no. 3 (2022): 1703-1713.
Turabian Style
Prabhakar, Sonar Ketan, et al. "IDENTIFICATION OF CAUSES OF TIME AND COST OVERRUN, IT’S IMPACT AND CONTROL IN METRO PROJECTS IN INDIA." International Journal of Advance Research and Innovative Ideas In Education 8, no. 3 (2022): 1703-1713.

Export Citation

Related Research

ENERGY ANALYSIS OF RESIDENTIAL BUILDING USING REVIT
Deepti et al. 2026 Civil Engineering
PDF Unavailable
Applications Artificial Intelligence and Machine Learning in Civil Engineering Domain
Abdus Salam Bakhtiyar Ahmed Dafedar et al. 2026 Civil Engineering
PDF Unavailable
Circular Economy in Civil Engineering
SHITALKUMAR S.DESHMUKH et al. 2026 CIVIL ENGINEERING
PDF Unavailable
kicthen organic waste as a material for vermiculture and a source of nutrients for plants
SANTOSH TAMMANNA BASARAGI et al. 2026 Civil Engineering
PDF Unavailable
STUDY ON SEISMIC ANALYSIS OF EARTH DAMS AND EMBANKMENT
Mr. Rahul Paikrao et al. 2025 Civil Engineering
PDF Unavailable