STUDY ON THE CAUSES OF DELAY IN A CONSTRUCTION PROJECT AND RECOMMENDATION
Abstract & Details
Research Area
CIVIL ENGINEERING
Keywords
Construction delay
delay mitigation
risks
consultants
clients and contractors
Abstract
The main aim of this paper was to find out the main causes of delay in construction projects in India. The research design was quantitative, where the data was collected from clients, consultants and contractors using questionnaires. The questionnaire had a list of delay causing factors of which the respondents were ask to rank each according to the 5 point likert scale. The data obtained were analyzed using the Statistical Program for Social Scientists (SPSS).
The results obtained indicate that the top major causes of delay were; fluctuation of prices of construction materials, shortage of materials, inaccurate time estimation, and errors during construction. In addition the top major effects of delay were; Cost overrun, acceleration of losses, time overrun, negative social impacts and litigation. Also the top major risks associated with construction delay were; too much pressure on project stake holders, price inflation of materials and overall project, disputes amongst project participants, project abandonment, overall cost increase and decline in revenue.
License
This work is licensed under a Creative
Commons
Attribution-ShareAlike 4.0 International License.
Author Information
| # | Name | Institute / Affiliation |
|---|---|---|
| 1 | AHMAD MONIS ANSARI | AL-FALAH UNIVERSITY |
How to Cite
Use the following formats to cite this article in your research.
APA Style
ANSARI, AHMAD MONIS (2019). STUDY ON THE CAUSES OF DELAY IN A CONSTRUCTION PROJECT AND RECOMMENDATION. International Journal of Advance Research and Innovative Ideas In Education, 5(4), 298-315.
MLA Style
ANSARI, AHMAD MONIS. "STUDY ON THE CAUSES OF DELAY IN A CONSTRUCTION PROJECT AND RECOMMENDATION." International Journal of Advance Research and Innovative Ideas In Education, vol. 5, no. 4, 2019, pp. 298-315.
IEEE Style
AHMAD MONIS ANSARI, "STUDY ON THE CAUSES OF DELAY IN A CONSTRUCTION PROJECT AND RECOMMENDATION," International Journal of Advance Research and Innovative Ideas In Education, vol. 5, no. 4, pp. 298-315, 2019.
Vancouver Style
ANSARI AHMAD MONIS. STUDY ON THE CAUSES OF DELAY IN A CONSTRUCTION PROJECT AND RECOMMENDATION. International Journal of Advance Research and Innovative Ideas In Education. 2019;5(4):298-315.
Harvard Style
ANSARI, AHMAD MONIS (2019) 'STUDY ON THE CAUSES OF DELAY IN A CONSTRUCTION PROJECT AND RECOMMENDATION', International Journal of Advance Research and Innovative Ideas In Education, 5(4), pp. 298-315.
Chicago Style
ANSARI, AHMAD MONIS. "STUDY ON THE CAUSES OF DELAY IN A CONSTRUCTION PROJECT AND RECOMMENDATION." International Journal of Advance Research and Innovative Ideas In Education 5, no. 4 (2019): 298-315.
Turabian Style
ANSARI, AHMAD MONIS. "STUDY ON THE CAUSES OF DELAY IN A CONSTRUCTION PROJECT AND RECOMMENDATION." International Journal of Advance Research and Innovative Ideas In Education 5, no. 4 (2019): 298-315.
Related Research
ENERGY ANALYSIS OF RESIDENTIAL BUILDING USING REVIT
PDF Unavailable
Evaluation of Pavement Distress and Maintenance Strategies for National Highway NH-448 (Ajmer to Beawar Section), Rajasthan
PDF Unavailable
Wind-Induced Productivity Loss in Pre-Engineered Building Erection: A Regression-Based Analysis from a High-Wind Zone Ajmer, (India)
PDF Unavailable
CEMENT TREATMENT OF A SILTY-CLAYEY SOIL FOR ROAD FOUNDATION LAYER: CASE OF RN43 FARATSIHO–SAMBAINA, MADAGASCAR
PDF Unavailable
Applications Artificial Intelligence and Machine Learning in Civil Engineering Domain
PDF Unavailable
Estimation of Roof Top Rainwater Harvesting Potential for Ground Water Recharging Considering Dominant Losses.
PDF Unavailable
Circular Economy in Civil Engineering
PDF Unavailable
kicthen organic waste as a material for vermiculture and a source of nutrients for plants
PDF Unavailable
STUDY ON SEISMIC ANALYSIS OF EARTH DAMS AND EMBANKMENT
PDF Unavailable