Study of Practices in Qualitative Risk Assessment, Project Time Management Tools & Techniques, Time & Cost Overrun
Abstract & Details
Research Area
Architecture & Planning
Keywords
Qualitative risk assessment
Tools & techniques
Project management
Time management
Safety
Abstract
It is essential to study the practices adopted in different regions for qualitative risk assessment in project and time management and measures taken to overcome the failures in overall project management. It can be learnt from such a study that whether the construction companies are following the project management tools and techniques for effective execution of the plan in completion of the project successfully. Different regions follow varied aspects of project management dependent on the resource availability, costs and labor work culture in the respective region. Certain regions may discover new models specific to their problems and introduce the same for effective realization of solutions. Identification of the risk factors affecting the project well in time is important so as to tackle with such risk factors.
Study shows that there is lack of usage of risk assessment tools and techniques during construction project management and hence affects on project time management, costs and labor intensive. Also it increases the risks during project execution and has hazards on health and safety. Time overrun and cost overrun are the main issues arisen due to improper project management.
License
This work is licensed under a Creative
Commons
Attribution-ShareAlike 4.0 International License.
Author Information
| # | Name | Institute / Affiliation |
|---|---|---|
| 1 | Ar. Hrushikesh A. Tarkasband | M. Arch (Architectural and Construction Project Management), SPSMBH's College of Architecture, Kolhapur |
| 2 | Prof. Ar. Sanjay D. Joshi | SPSMBH's College of Architecture, Kolhapur |
How to Cite
Use the following formats to cite this article in your research.
APA Style
Tarkasband, Ar. Hrushikesh A. & Joshi, Prof. Ar. Sanjay D. (2022). Study of Practices in Qualitative Risk Assessment, Project Time Management Tools & Techniques, Time & Cost Overrun. International Journal of Advance Research and Innovative Ideas In Education, 8(1), 1307-1320.
MLA Style
Tarkasband, Ar. Hrushikesh A., and Prof. Ar. Sanjay D. Joshi. "Study of Practices in Qualitative Risk Assessment, Project Time Management Tools & Techniques, Time & Cost Overrun." International Journal of Advance Research and Innovative Ideas In Education, vol. 8, no. 1, 2022, pp. 1307-1320.
IEEE Style
Ar. Hrushikesh A. Tarkasband and Prof. Ar. Sanjay D. Joshi, "Study of Practices in Qualitative Risk Assessment, Project Time Management Tools & Techniques, Time & Cost Overrun," International Journal of Advance Research and Innovative Ideas In Education, vol. 8, no. 1, pp. 1307-1320, 2022.
Vancouver Style
Tarkasband Ar. Hrushikesh A., Joshi Prof. Ar. Sanjay D.. Study of Practices in Qualitative Risk Assessment, Project Time Management Tools & Techniques, Time & Cost Overrun. International Journal of Advance Research and Innovative Ideas In Education. 2022;8(1):1307-1320.
Harvard Style
Tarkasband, Ar. Hrushikesh A. & Joshi, Prof. Ar. Sanjay D. (2022) 'Study of Practices in Qualitative Risk Assessment, Project Time Management Tools & Techniques, Time & Cost Overrun', International Journal of Advance Research and Innovative Ideas In Education, 8(1), pp. 1307-1320.
Chicago Style
Tarkasband, Ar. Hrushikesh A. and Prof. Ar. Sanjay D. Joshi. "Study of Practices in Qualitative Risk Assessment, Project Time Management Tools & Techniques, Time & Cost Overrun." International Journal of Advance Research and Innovative Ideas In Education 8, no. 1 (2022): 1307-1320.
Turabian Style
Tarkasband, Ar. Hrushikesh A. and Prof. Ar. Sanjay D. Joshi. "Study of Practices in Qualitative Risk Assessment, Project Time Management Tools & Techniques, Time & Cost Overrun." International Journal of Advance Research and Innovative Ideas In Education 8, no. 1 (2022): 1307-1320.
Related Research
BAMBOO AS A MATERIAL
PDF Unavailable
The impact of le Corbusier on indian Architects such as B.V. Doshi and Charles Correa.
PDF Unavailable
EFFECT OF WINDOWS TO WALL ORIENTATION ON ENERGY EFFICIENCY IN INSTITUTIONAL BUILDINGS IN YOLA
PDF Unavailable
A Review of the Impact of Noise Pollution on Students in Architecture Studios in Universities
PDF Unavailable
SUSTAINABILITY DEVELOPMENT INDEX FOR BUILDINGS
PDF Unavailable
BIOPHILIC NET-POSITIVE ARCHITECTURE ESPOUSES PASSIVE DESIGN STRATEGIES FOR A HEALTHY SUSTAINABLE BUILT ENVIRONMENT: OVERVIEW
PDF Unavailable
Strategies for Effective Procurement of Sustainable Public Building Infrastructure Projects
PDF Unavailable